8.5 Activity Related Standards
8.5.1 Construction
In Kaitiaki (Conservation) zones or in the vicinity of Identified Significant Features as shown on the planning maps, the placement of underground powerlines or telecommunication lines in significant landscape areas shall be a permitted activity. No trees or shrubs are to be removed and there shall be full reinstatement of the ground and vegetation immediately after the utility is installed to a state compatible with the original and surrounding vegetation except where the activities are provided for on a Development Concept Plan. See Schedule 5.
Objectives/Policies | ||
3.1.2.1 | O1 | P1 |
3.1.2.2 | O1 | P2, P3, P4 |
3.7.2.1 | O1 | P1, P2 |
Explanation
Particular regard must be given to construction within especially sensitive areas such as the Kaitiaki (Conservation) Zone or Identified Significant Features. While underground power and telecommunication lines are provided for as a permitted activity it is essential that the impact of their construction is minimised immediately.
8.5.2 Protection of Publicly Owned Flood Control and Drainage Assets
- Permitted Activities
- Stock-proof fences.
- Farming of grazing animals.
- Discretionary Activities
- Separation for Maintenance
The following activities shall have discretionary activity status within 20 metres (horizontal line) of a public drain (measured from the lip of the drain) or the landward toe of a stopbank, or on a stopbank, or on
the berm between a stopbank and a river or drain, or within a 20 metres radius of a pump station.
- The growing or allowing to grow of any shrub, hedge or tree or part thereof.
- The digging of any drain or excavation that will interfere with access of WRC workers, contractors and machines.
- The erection of any shelter fence, building or construction.
- The construction of any road or race for the passage of stock or vehicles.
- Stopbanks.
The excavation or the digging of any drain within 20 metres of any stopbank.
- Separation for Maintenance
Advice Note
See also Sections 7, 9, 10, 11 and 12.
Objectives/Policies | ||
3.2.2.1 | O1 | P1, P2, P3, P4 |
3.7.2.1 | O1 | P2, P4 |
Explanation
Protection of flood control and drainage works is of particular importance to the District.
The activities allowed in the vicinity of these works are listed separately to emphasise the importance of the works.
Discussions are continuing with the Regional Council to ensure a co-ordinated approach is maintained.