About the Matamata accessibility improvements
Accessbility work planned for Matamata
We are improving accessibility in the Matamata town centre. Work is due to take place from February 2025.
In 2021 to 2023, we carried out accessibility audits in the Matamata, Morrinsville and Te Aroha town centres and worked closely with accessibility groups to see how we can improve journeys for those who get around on foot, push prams or use mobility aids.
Thanks to external funding, we are able to action just over 50% of the upgrades and improvements identified in the audits.
Here is the work we have planned for Matamata town centre. You can also see the locations, images and descriptions of improvements on this interactive Google Earth map of Matamata.
Broadway (west side of Waharoa East Road) |
Regrade concrete footpath. Install yellow tactile pavers. |
46 Broadway (mobility park) |
Cut down kerb, regrade and re-lay pavers. |
48 Broadway |
Regrade and re-lay pavers. |
54-56 Broadway |
Regrade and re-lay pavers. |
Broadway crossing (Bell & Graham to Osteria - north side) |
Replace red tactile pavers with yellow. |
Broadway crossing (Bell & Graham to Osteria – central island) |
Regrade and re-lay pavers, including path to seats. Tidy up along the gardens, regrade grass area to match new paver levels and re-grass. |
Broadway crossing (Bell & Graham to Osteria – south side) |
Replace red tactile pavers with yellow. |
Broadway (outside Bell & Graham Solicitors) |
Regrade and re-lay pavers. Replace red tactile pavers with yellow. |
Broadway (ANZ crossing Arawa Street) |
Replace red tactile pavers with yellow. |
Broadway crossing (Ronnies to central island to Tonezone) |
Replace all red tactile pavers with yellow. |
Broadway (mobility park outside Bay Audiology) |
Cut down kerb, regrade and re-lay pavers. |
Broadway crossing (Fez Kebab to Triton Hearing - north side) |
Replace red tactile pavers with yellow. |
Broadway crossing (Fez Kebab to Triton Hearing - central island) |
Cut down kerbs both ends of the crossing, regrade and re-lay pavers and replace red tactile pavers with yellow. |
Broadway crossing (Fez Kebab to Triton Hearing – south side) |
Replace red tactile pavers with yellow. |
Broadway (Tainui Street to Meura Street) |
Replace existing concrete footpath. |
Tainui Street (crossing at Broadway) |
Replace PVC tactile pavers with yellow tactile pavers both sides. |
Broadway (mobility park outside Paper Plus) |
Cut down kerb, regrade and re-lay pavers. |
Broadway (mobility park outside Kowhai Creamery). |
Cut down kerb, regrade and re-lay pavers. Move rubbish bin. |
Rawhiti Ave (crossing north-east side by Arawa Street) |
New crossing point - 3m east of existing. Install asphalt ramp with steel plate to give step-free access. |
Rawhiti Ave (south-east side by Arawa Street) |
New crossing point - 3m east of existing. Install asphalt ramp with steel plate to give step-free access. |
88-90 Arawa Street |
Replace existing concrete footpath. |
Arawa Street (at Gouk Street crossing – north side) |
Cut down kerb and replace concrete footpath. |
Arawa Street (mobility park outside Stirling Sports) |
Cut down kerb, regrade and re-lay pavers. |
Arawa Street (mobility park outside Shosha) |
Cut down kerb, regrade and re-lay pavers, move stormwater outlets to south side of car park. |
Arawa Street Crossing (Life Pharmacy - Stirling Sports) |
Install yellow tactile pavers on both sides. |
Arawa Street crossing (O-Del-Emz - Harcourts) |
On both sides - remove bollards, regrade and re-lay pavers, install yellow tactile pavers. |
Hetana Street crossing (at Arawa Street) |
Install yellow PVC peel and stick tactiles in centre island. |
Tui Street crossing (at Arawa Street end) |
Install yellow tactile pavers to both sides and PVC peel and stick tactiles in centre island. |
Tui Street (mobility park opposite FMG) |
Reinstate kerb, re-grass. |
Tainui Street (Aon to Rabobank) |
Regrade and re-lay pavers. |
4 Tainui Street |
Replace concrete footpath. |
Latest news
Pedestrian crossing coming to Meura Street, Matamata
Waharoa bus stop upgrades
No more funding for Transport Choices projects
New pop-up pump track arrives just in time for summer
Blessing marks opening of Morrinsville Recreation Ground perimeter path
Waka Kotahi Transport Choices funding on hold
Project Timeline
Construction dates
We anticipate the Matamata and Morrinsville CBD accessibility improvements to start February 2025 and take up to 10 weeks to complete. We’ll provide updates closer to the time.