Please be advised Resource Consents lodging and processing will be paused from the 20 December 2025 – 10 January 2026 as per the Resource Management Act, days within this period are not considered as working days. Thank you for your patience and we wish you a safe and happy festive season.
Appendix 8: Motumaoho Quarry, Winstone Aggregates Ltd
Noise Control Boundary

NOISE
The noise level from operational activities (excluding maintenance and construction activity) within or from the use of the Motumaoho Quarry site shall not exceed the following levels when measured at any point beyond the Quarry Noise Control Boundary.
| PERIOD October to March Monday to Saturday 6.30am to 6.00 pm |
NOISE LEVEL 55 dBA L 10 |
| April to September Monday to Saturday 6.30am to 5.00pm And, provided that a nominated representative of the residents of Harbottle Road has been informed, during additional hours as follows: Monday to Friday 5.00pm to 6.00pm |
55 dBA L 10 |
| At all other times |
45 dBA L 10 |
| Everyday 10.00pm to 6.30am | 70 dBA Lmax |
The General Provisions of Rule 5.2.1 shall be taken into account except that the duration of any individual measurement period shall be not less than 30 minutes.